MRP Planning, Processing and Results: Advance Plan

Advance Plan

Advance Plan

After selecting plan items in the Production Plan Full Listing window, clicking on the Advance Plan button will open this window.

Without the Use Make calendar checkbox checked, processing will simply add calendar days. When checked, each plan item will be advanced by the entered number of Make calendar days. If you exceed the Make calendar, items will be given the final calendar date.

Field

Description

Number of days

Enter the number of days you wish to advance production plan items by.

Use Make calendar

Check, if the days entered should relate to the Make Calendar, I.E. working days.

Button

Action

Cancel

Aborts the process currently in session. The keyboard equivalent is the Esc key for Windows computers and Command-.(full stop or period) for the Mac.

OK

The OK button updates the data you have entered, or confirms the selection and/or processes the function you have called.

See also: –

Compiled in Program Version 5.10. Help data last modified 18 Oct 2001 15:11:00.00. Class wPrdAdv last modified 18 Feb 2015 01:54:47.

Was this article helpful?

Related Articles

Contents

Need Support?

Can't find the answer you're looking for?
Contact Support

Get started.

Try our state-of-the-art ERP Manufacturing Software today.