Process Times Update
This function calculates optionally set and run times for assembly route operations from work history. It applies to all operations for an assembly part. It is particularly useful for assemblies made for the first time where times are initially not known and shopfloor times are being recorded.
First choose from the checkbox option what you wish to update. Then select the assembly parts you want to apply the update to in the Parts ScratchPad. Drag these selected lines and drop them on the window.
An Alert Message will warn you of any anomalies encountered such as missing history for an operation.
Field |
Description |
---|---|
Update Set Time |
Check to update set times. |
Only If Zero |
Check if the update is to apply only if the current value is zero. |
Update Runtime |
Check to update run times. |
Only If Zero |
Check if the update is to apply only if the current value is zero. |
Update Lag Time to: |
Check this option to update the operation lag times. |
Lag Time |
To apply a lag time to all operations, enter a lag value here. |
Only If Zero |
Check if the update is to apply only if the current value is zero. |
Compiled in Program Version 5.10. Help data last modified 17 May 2012 02:10:00.00. Class wProOpTimes last modified 4 Aug 2015 16:38:27.